Home Page >
Timothy R. Hughes' Articles >
Electrical Contractor Magazine
Timothy R. Hughes, Esq.
Hughes & Associates, P.L.L.C.
Subcontractors are often bound to extremely harsh contractual terms. It is
critical to examine your subcontracts carefully and clearly understand
what you are agreeing to do. What follows are some pointers regarding
contractual issues that can create serious problems.
1. Ensure A Clearly Defined Scope of Work
The quickest and surest way into litigation is a poorly defined scope of
work. If the parties fail to have a clear and mutual understanding of what
a subcontractor is hired to do, this situation invites disputes. Perhaps
my viewpoint is skewed in that I see many cases that are in litigation.
Nevertheless, I am continually surprised at how many of my cases have
significant gaps or vague areas in definition of scope of work.
This problem seems particularly true in mechanical, electrical, and
plumbing disciplines. Often, drawings are depicted in a very schematic
fashion. This lack of clear definition of the precise scope of work in the
drawings can lead to substantial disagreements as to how much work the
subcontractor is expected to perform. The essence of a good contract is
one that is simple, clear and well defined. If there are vague points in
the scope of work, you must approach the project bidding from a worst case
scenario on exactly how much work you will be required to perform.
2. Understand the Scheduling Requirements
As with poorly defined scopes of work, it is truly impossible to properly
price a job unless you understand the schedule and what it will take for
you to complete your efforts on time. Time means money in all businesses,
but on construction projects the translation is literal. In addition,
there is no more complex case to litigate than a complicated delay claim.
The cases are heavily fact intensive and require extensive and expensive
expert witness analysis. Avoid these expenses if possible by understanding
the schedule requirements before you start work.
As with scope of work issues, electrical trades are notoriously subject to
delay related issues. Electrical contractors often face conflicting code
decisions. For example, the drawings are reviewed and approved. Field
inspectors often change requirements for fire alarms, alarm panel
annunciation, and wiring in the field. These field directions can lead to
extensive changes in the scope of work and delays.
Further, electrical contractors are often competing for limited above
ceiling space with other trades. The above ceiling space is often a
schematic wasteland of conflicts. These conflicts amongst trades lead
naturally and necessarily to increased construction costs and delays.
On a final note, general contractors are including form scheduling clauses
that are more and more harsh. Many general contractors include clauses
that attempt to shift responsibility for all delays downstream to the
subcontractors. Depending on your state’s law, there may be some arguments
against these harsh clauses on your project; however, such arguments
usually only arise on the context of litigation. It is better to attempt
to reduce those risks in advance of performance.
3. Be Careful of Incorporated Standards and
Terms
From my recent experience, compliance with incorporated standards is a
growing exposure area for electrical contractors. It has become common for
architects and engineers to incorporate extensive industry standards and
codes by reference into specifications. For example, for electrical
contractors, you can probably expect for specifications to incorporate by
reference code requirements from the National Electric Code.
The potential rub occurs where there is something omitted from the
drawings and specifications that is arguably inferable from the NEC
standards. If you are contractually bound to install all elements required
for “code compliance”, you may be liable for all additional work that was
left out of the drawings. Further, conflicts can and do occur between the
base specifications, applicable codes, and the incorporated standards of
performance. You may be held liable to perform the most restrictive,
expensive, and time consuming requirements of performance.
4. Beware of Broad Form Indemnification
Clauses
Indemnification clauses are likely the most dangerous contractual terms
found in an agreement. A broad form indemnification clause can potentially
make you liable for damages that were primarily caused by a subcontractor.
Indeed, in some states, a broad form indemnification clause can even make
you liable to indemnify the general contractor where the general
contractor was solely responsible for the claimed damages!
The main point here is you need to closely analyze your contracts. Hiring
a lawyer for even a quick review of the contract is generally a very good
idea. If you are facing an indemnification clause, it is far better for
you to understand the risks you are signing on to at the beginning of a
job instead of learning at the end of litigation.
On a final note, indemnification clauses can create additional liability
risks beyond the types of claims covered. Specifically, you can be held
liable for a variety of additional damages that may not be recoverable for
other types of claims, such as attorney fees and litigation expenses. Your
insurance carrier may have additional arguments for why it is not
obligated to defend and indemnification claims. Given all these factors,
indemnification claims are particularly dangerous and such clauses warrant
very close scrutiny prior to signing a contract.
Conclusion
Understanding the terms of the deal you are signing is critical to
reducing risk. You may be able to negotiate more favorable terms. You will
have a better understanding of what your risks are and can handle a
project accordingly. To avoid this process and simply fly blind into the
project can place you or your business in serious jeopardy in the event of
litigation.

Timothy R. Hughes, Esq., is the principal of the Northern
Virginia law firm of Hughes & Associates, P.L.L.C. He specializes in
construction litigation, corporate and business related representation,
and complex civil litigation. He may be reached at
tim@hughesnassociates.com.
Printed with permission
from
Electrical Contractor
Top of page
Timothy R. Hughes' Articles | Home Page |
Contact Us