Home Page >
Timothy R. Hughes' Articles >
Electrical Contractor Magazine
Timothy R. Hughes, Esq.
Hughes & Associates, P.L.L.C.
Subcontractors often do not have the complete
documentation of their own contracts. Similarly, subcontractors often do
not know exactly what they have agreed to. It is absolutely critical that
you obtain all the documents that comprise your subcontract and that you
understand your rights, duties, and liabilities.
The Incorporated General Contract
Subcontracts generally have a term incorporating various materials by
reference. Such terms often incorporate the prime contract by reference
and establish that one document controls. In my experience, very few
subcontractors ever bother to even request the prime contract let alone
read it. This means that subcontractors are agreeing to contract terms
they have never seen.
This can naturally create problems. For example, the subcontractor may
have agreed to a term that it can only recover on a claim if the
contractor recovers on a claim from the owner. Further, the general
contract may have explicitly stated that the only remedy for a delay is a
time extension and that there will be no financial recovery for delays on
the project. A similar result can occur with what circumstances can give
rise to a delay claim. It is critical to know these matters in advance or
a subcontractor may be taking on risks that can easily swamp a business.
Scope of Work – Incorporation of Missing
Specifications
Many subcontracts provide for a specific scope of the subcontractor’s work
on the job. The same subcontract generally lists the “contract documents”
which apply to the work in question. That list often includes a kitchen
sink of each drawing and the entirety of the specifications.
In my experience, subcontractors tend to obtain the absolute minimum
possible portion of the contract documents that apply to their specific
work. While the subcontract may incorporate each of the drawings, it is a
rare electrical subcontractor that obtains the architectural drawings.
Some even skip the mechanical and electrical drawings, although to do so
represents an extreme risk given the competition amongst the MEP trades
for above ceiling space.
Even more often, the subcontractor only obtains a truncated set of the
specifications. This set of the specifications often only includes the
section addressing their specific scope of work. Failing to obtain the
specifications of other trades can lead to coordination problems.
Sometimes, requirements of one trade’s work are blended into another
trade’s specifications and without the specifications the subcontractor
has no idea.
Often, the truncated set does not even include the general conditions.
Failing to obtain the general conditions can lead a subcontractor to fly
blind during the project about critical contractual process and procedure.
Timing and requirements for submission of shop drawings may be missing.
Specific terms for substitutions of materials may be missing. Missing even
a single element of the contract can turn a project into a liability
minefield.
The Incorporated Standards
At the risk of repeating prior articles, subcontractors should be very
wary of incorporated standards for performance. This is particularly true
of specifications which incorporate compliance with an applicable building
code as a requirement of performance.
The Example
I represented a general contractor on a very messy project. They had hired
various subcontractors. The subcontracts incorporated the prime contract
by reference. The specifications incorporated compliance with the NEC by
reference in addition to laying specific elements of construction.
During construction, local code officials insisted on additional items of
electrical work to comply with the NEC. The electrical subcontractor
performed the work and requested additional money. Unfortunately, they
were not familiar with the provisions of the owner/general contractor
agreement which required written submission and approval by the owner
before additional work. In addition, the subcontractor was arguably
required to perform all the additional work as part of the base contract’s
requirement to comply with the code.
Conclusion
The end of the story is quite unhappy. The project ground to a halt. The
electrical subcontractor ended in bankruptcy and shut down its operations.
While reading all the documents is no guarantee, it certainly is a start
to avoiding this fate.

Timothy R. Hughes, Esq., is the principal of the Northern
Virginia law firm of Hughes & Associates, P.L.L.C. He specializes in
construction litigation, corporate and business related representation,
and complex civil litigation. He may be reached at
tim@hughesnassociates.com.
Printed with permission
from
Electrical Contractor
Top of page
Timothy R. Hughes' Articles | Home Page |
Contact Us